Design-Build Bridge Replacement Hollis E. Jennings

Berkely 6.jpg
Berk 8.jpg
Berk 7.jpg
Berkley 1.jpg
Berkley 2.jpg
Berkley 3.jpg
Berkely 4.jpg
Berkely 5.jpg

PROJECT DETAILS:

This design-build project required the construction of a new bridge over 4 lanes on Route 24 during a 6-week shutdown period. MAS, WSP and Fort Miller worked to design a concept consisting primarily of precast substructure components and prefabricated bridge units (PBUs). MAS demolished the existing bridge and installed the new structure ahead of the 6-week milestone. This project has been awarded the CMAA Project Achievement Award in the <$10Mil category.

OWNER: MassDOT

VALUE: $5.8M

LOCATION: Berkley, MA